Rama III Oil Leak Source Found, Full System Inspection Ordered

Thitipas Chotedechachainan, secretary to the energy minister, said investigators had identified the source of an oil leak on Chuea Phloeng Road in Bangkok’s Rama III area following an inspection of the site.

The leak was found beneath a pipe sleeve measuring approximately 1.8 metres long. As the sleeve was tightly secured to the fuel pipeline and could not be removed intact, workers changed their approach and began cutting it away section by section to examine the pipe in detail.

“The Department of Energy Business has told Bangchak Group to bring in a qualified third party with ultrasonic testing (UT) scanning equipment to assist with the inspection, as the equipment can examine materials and detect internal cracks without damaging the item being tested.”

An ultrasonic scan conducted the previous evening located the leak about 1.2 metres from the end of the sleeve. The damaged section measured approximately 6.6 centimetres long and seven millimetres deep.

Engineering and technical teams are expected to accelerate repairs using a pipe-wrapping method. After the repair material has dried, officials will conduct another ultrasonic scan and at least two additional inspections using other equipment.

The pipeline must pass all checks confirming that the repaired section is no longer leaking before a pressure test can be carried out.

“We will not stop after repairing the point found today. We must ensure that the entire pipeline system is safe.”

“Once the pipeline has passed the testing stage, an intelligent pigging test will be conducted, using an intelligent pig to inspect the inside of the pipe along the entire pipeline, covering about 32 kilometres, to assess its thickness and identify any additional points at risk of leakage.”

“If any risk points are found, the company must prepare a pipe replacement plan. It must also submit a plan to replace the pipe at the currently damaged point in line with engineering principles, with Department of Energy Business officials closely supervising the work and testing.”

The Department of Energy Business has also ordered the company to submit the pipeline’s maintenance records, including details of every location where protective sleeves have been installed.

Officials will review the records to determine whether any other sections have previously leaked or could be vulnerable to similar damage.

Particular attention will be given to pipeline sections near piers, which must be surveyed before a new alignment is planned to reflect current site conditions and help prevent future incidents.

Authorities stressed that the response would involve an inspection of the entire system, rather than repairs being limited to the identified leak.

The Ministry of Energy and the Department of Energy Business will supervise the repairs, pressure testing and full pipeline inspection to ensure the work meets engineering standards. The measures are intended to confirm the safety of the oil transport system and reduce the possibility of another leak.